II. Utility Assessment Plans
Development of an assessment plan for assessing the energy and water management reduction measures:
- In 1997 the University commissioned Shah Smith & Associates, Inc. to undertake an Energy Assessment Report. This report included 32 buildings with a gross square footage of 1,424,000 square feet. Energy Cost Reduction Measures (ECRM) were implemented and completed by November of 2000. The remaining eight (8) buildings had the PUA done in FY 2004. The following is the Shah Smith & Associates report:
TEXAS LoanSTAR PROGRAM
ENERGY ASSESSMENT REPORT
FOR
Texas A&M University - Kingsville
1255 Retama Drive
Kingsville, TX 78363
Conducted by:
Shah Smith & Associates, Inc.
2825 Wilcrest, Suite 350
Phone: (713)780-7563
Fax: (713)780-9209
September 25, 1997
Number of Buildings: 32
Total Gross Square Footage: 1,424,000
TABLE OF CONTENTS
Page
COVER SHEET 1
TABLE OF CONTENTS 2
PREFACE 3
BACKGROUND 3
SUMMARY NARRATIVE 3
ACKNOWLEDGMENTS 3
EXECUTIVE SUMMARY 4
BUILDINGS/FACILITIES ANALYSIS 4
FIGURE 1 – CAMPUS MAP 5
COMPOSITE PROJECT SUMMARY 6
SUMMARY OF PROJECT 8
TABLE 1 - SUMMARY OF INDIVIDUAL ECRMs 9
BASE YEAR ENERGY CONSUMPTION AND COSTS 10
TABLE 2 - BASE YEAR ENERGY CONSUMPTION DATA 10
METERING INFORMATION 11
TABLE 3 - METER DATA 11
UTILITY RATE SCHEDULE ANALYSIS 12
ELECTRIC UTILITY RATE SCHEDULE ANALYSIS 12
GAS UTILITY RATE SCHEDULE ANALYSIS 15
FACILITY DESCRIPTIONS 16
FACILITY DESCRIPTION 16
TECHNICAL ANALYSIS 21
ECRM No. 1 21
ECRM No. 2 23
ECRM No. 3 24
ECRM No. 4 25
ECRM No. 5 27
ECRM No. 6 28
ANALYST CERTIFICATION 29
APPENDICES
Appendix A – Savings Calculations
Appendix B – Electric Bills
Appendix C – Electric Rates/Rebates
Appendix D – Gas Bills
Appendix E – Trace Input
Appendix F – Trace Output
Appendix G – Existing Building Data
Appendix H - KY Pipe Data
Appendix I – January/February Electric Load Profile
Appendix J – ECRM Cost Estimates
PREFACE
BACKGROUND
The Texas A&M University – Kingsville (TAMU-K) campus has thirty-three (33) buildings which are currently being cooled and/or heated from two central plants (see Figure 1). Of these, twenty(20) buildings are being served via a two-pipe hydronic system. This two pipe system not only limits the university’s ability to control building comfort but it costs additional energy in the switchover process by heating up chilled water and cooling down heating water.
The two existing central plants have a combined installed capacity of 4500 tons. The chillers range in age from 21 to 38 years and utilize R-11 (CFC) as the refrigerant. TAMU-K indicates that the average chiller efficiency is 0.90 kW/ton, which is based on field measurements.
The existing pumping system consists of primary pumps located in the two central plants and secondary pumps located in the individual buildings. In some buildings, the secondary pumps have been removed and the primary pumps are utilized to pump through those building. Most buildings on the system utilize 3-way valves to bypass the coils during times of low demand. This essentially creates a constant volume system and does not allow for reduction in pumping energy at times of low load.
TAMU-K has initiated the “Campus HVAC System Improvements Project” which is intended to implement the recommended Energy Cost Reduction Measures (ECRMs) as well as other work, but the available funding will not cover the estimated project cost. However, TAMU-K has sufficient funding to buy down the cost of the ECRMs to the composite 8 year payback limit.
Shah Smith & Associates, Inc. has been selected to analyze the following Energy Cost Reduction Measures:
1. Install electric heat in buildings currently served from two-pipe system.
2. Replace all existing chillers with more efficient chillers (5 – 625 ton, non-CFC chillers).
3. Replace 3-way valves with 2-way valves.
4. Install variable frequency drives (VFD) on the primary distribution pumps.
5. Install a campus energy management system (EMS).
6. Install a thermal energy storage system.
SUMMARY NARRATIVE
This study was performed under the Texas LoanSTAR Program guidelines as administered by the State Energy Conservation Office. The purpose is to identify energy cost reduction measures (ECRMs) which, when implemented, will result in significant energy cost savings for the borrower. The savings calculations are made using sound, accepted fundamentals of engineering and current utility rate schedules.
ACKNOWLEDGMENTS
The staff of Shah Smith and Associates, Inc. would like to extend its thanks and appreciation to Texas A&M University - Kingsville and the Texas A&M University System and their staffs for assistance on the procurement of building data and operation schedules. Special thanks to Mr. E. Ervin Linnstaedter, Texas A&M System Mechanical Engineer, for devoting time, insight and resources. Further thanks are extended to Mr. Buck Shaw, Assistant Director of Physical Plant and other operation and maintenance personnel for their support and helpfulness.
TEXAS LoanSTAR PROGRAM
Energy Assessment Report of
Texas A&M University - Kingsville
Contact Person: Mr. Emil Ervin Linnstaedter, System Mechanical Engineer
The Texas A&M University System
Facilities Planning Division
UMS Box 1586
College Station, TX 77843
Phone: (409)845-8857
EXECUTIVE SUMMARY
BUILDINGS/FACILITIES ANALYZED
This Energy Cost Reduction Analysis applies to the two central plants and to the campus buildings that currently receive their thermal utilities from them.
|
FI # |
Bldg Name |
Bldg Type |
Bldg Area (Sq. Ft.) |
|
501 |
College Hall |
Administration |
49999 |
|
502 |
Manning Hall |
Classroom |
44989 |
|
503 |
Hill Hall |
Classroom |
24223 |
|
505 |
Speech/Music |
Classroom |
41792 |
|
506 |
Bailey Art ('88) |
Classroom |
11707 |
|
507 |
Nierman Hall |
Classroom |
41288 |
|
509 |
Human Sciences (Home Econ.) |
Classroom |
19852 |
|
512 |
Kleberg Engineering Hall |
Classroom |
41254 |
|
517 |
Kleberg Bldg for Agriculture |
Classroom |
21203 |
|
520 |
Art Addition ('72) |
Classroom |
9498 |
|
521 |
ROTC Bldg |
Classroom |
11264 |
|
523 |
Fore Hall |
Classroom |
23312 |
|
524 |
Biology & Earth Science Hall |
Classroom |
41705 |
|
525 |
Health & Rec. Bldg |
Activity |
32436 |
|
526 |
Jernigan Library |
Student Services |
140147 |
|
527 |
Gross Industrial Arts |
Classroom |
21469 |
|
528 |
Steinke PE Center |
Activ./Spec. Events |
99034 |
|
533 |
Rhode Hall |
Classroom |
76032 |
|
535 |
Business Admin |
Classroom |
42595 |
|
543 |
Dotterweich |
Classroom |
12781 |
|
544 |
Howe Ag Bldg |
Classroom |
21913 |
|
550 |
McNeil Engineering |
Classroom |
14873 |
|
600 |
Jones Auditorium |
Special Events |
23020 |
|
700 |
Student Health |
Student Services |
6194 |
|
725 |
Student U/Bookstore |
Student Services |
91887 |
|
745 |
Lewis Hall |
Dormitory |
60064 |
|
746 |
Eckhardt Hall |
Dormitory |
19868 |
|
747 |
Poteet Hall |
Dormitory |
71648 |
|
748 |
Lynch Hall |
Dormitory |
47391 |
|
749 |
Martin Hall |
Dormitory |
87650 |
|
750 |
Bee County(now Health/Wellness) |
Classroom |
9240 |
|
752 |
Turner-Bishop |
Dormitory |
163370 |
|
603 |
Art Annex |
Art Studio |
2000 |
COMPOSITE PROJECT SUMMARY
ECRM No. 1:
Installation of electric heat to provide for simultaneous cooling and heating in the buildings currently served via a two-pipe hydronic system. The affected buildings are listed below:
|
Hill Hall |
|
Speech/Music |
|
Bailey Art ('88) |
|
Human Sciences (Home Econ.) |
|
Kleberg Bldg for Agriculture |
|
Art Addition ('72) |
|
ROTC Bldg |
|
Fore Hall |
|
Biology & Earth Science Hall |
|
Health & Rec. Bldg |
|
Jones Auditorium |
|
Student Health |
|
Eckhardt Hall |
|
Poteet Hall |
|
Lynch Hall |
|
College Hall |
|
Lewis Hall |
|
Art Annex |
|
Martin Hall |
|
Turner-Bishop |
ECRM No. 2:
Replacement of all existing chillers in the two central plants with more efficient, non-CFC chillers.
ECRM No. 3:
Installation of Energy Management System (EMS) to efficiently control the electric heat installed under ECRM
No. 1.
ECRM No. 4:
Replace the majority of the 114 existing 3-way valves with 2-way valves at building AHUs to reduce pumping energy at low load conditions. Some existing 3-way valves will remain in the system to maintain minimum flow requirements. It is anticipated that 3-way valves will be replaced in the following buildings:
|
College Hall |
|
Manning Hall |
|
Hill Hall |
|
Speech/Music |
|
Bailey Art ('88) |
|
Art Annex |
|
Nierman Hall |
|
Human Sciences (Home Econ.) |
|
Kleberg Engineering Hall |
|
Kleberg Bldg for Agriculture |
|
Art Addition ('72) |
|
ROTC Bldg |
|
Fore Hall |
|
Biology & Earth Science Hall |
|
Health & Rec. Bldg |
|
Jernigan Library |
|
Gross Industrial Arts |
|
Steinke PE Center |
|
Business Admin |
|
Dotterweich |
|
Howe Ag Bldg |
|
Jones Auditorium |
|
Student Health |
|
Lewis Hall |
|
Eckhardt Hall |
|
Poteet Hall |
|
Lynch Hall |
|
Martin Hall |
|
Bee County |
|
Rhode Hall |
|
Bookstore |
ECRM No. 5:
Install variable frequency drives on primary pumps located in the two central plants. This ECRM does not appear to offer much savings above the savings realized by ECRM No. 4 listed above. SSA does not recommend the implementation of this ECRM.
ECRM No. 6:
Install a chilled water thermal energy storage system to transfer electrical demand to off-peak hours. CP&L’s current rate structure does not encourage thermal storage. SSA does not recommend the implementation of this ECRM.
|
|
|
SUMMARY OF PROJECT |
|
||
|
Category III Total |
|
||||
|
KWh Savings: |
2,643,876 |
kWh/yr |
|||
|
Demand Savings: |
23,006 |
kW/yr |
|||
|
Gas Savings: |
5,195 |
MCF/yr |
|||
|
Btu Savings: |
36,020 |
MMBtu/yr |
|||
|
Cost Savings: |
259,018 |
$/yr |
|||
|
Base Year Cost Red.: |
16.9 |
% |
|||
|
Implementation Cost(1): |
3,045,990 |
$ |
|||
|
Simple Payback: |
11.8 |
Years |
|||
Note:
(1) Implementation cost has CP&L’s Rebate included.
This report identifies capital-intensive projects which, if implemented in the form recommended, will result in the savings and costs summarized above. The savings for the recommended composite project listed above account for interdependence of savings of individual ECRMs. Costs for the project likewise account for savings which accrue from installing several ECRMs at once and for utility rebates which will lower project cost.
SPECIAL CONSIDERATIONS
TAMU-K will contribute the funds required to buy down the project payback to the composite 8 year limit. The required amount, $973,846, will come from funds already budgeted for the “Campus HVAC System Improvements Project”.
TABLE 1. SUMMARY OF INDIVIDUAL ENERGY COST REDUCTION MEASURES
|
ECRM No. |
ECRM Title |
Annual Savings |
Implementation Cost ($) (4) |
Simple Payback (yrs.) |
Estimated Project Lifetime (yrs.) |
|||
|
|
|
Electric Energy (kWh/yr.) |
Demand (kW/yr.) |
Natural Gas (MCF/yr.) |
Cost ($/yr.) |
|
|
|
|
1 |
Install Electric Heat |
(1)<542,760> |
10,737 |
5,195 |
134,760 |
1,132,060 |
8.4 |
25 |
|
2 |
Replace Existing Chillers |
2,395,876 |
10,337 |
0 |
97,836 |
(2) 1,594,000 |
16.3 |
25 |
|
3 |
Install EMS |
0 |
1,036 |
0 |
11,200 |
159,430 |
14.2 |
25 |
|
4 |
Replace 3-way Valves |
248,000 |
896 |
0 |
15,222 |
160,500 |
10.5 |
25 |
|
5 |
Install VFDs on Primary CHWPs |
(3) 15,171 |
(3) 12 |
0 |
(3) 316 |
(3) 85,600 |
N/A |
25 |
|
6 |
Install Thermal Storage |
0 |
(3) 9652 |
0 |
(3) 91,665 |
(3) 856,000 |
N/A |
25 |
|
TOTAL
|
2,643,876 |
23,006 |
5,195 |
259,018 |
3,045,990 |
11.8 |
25 |
|
Note:
(1) Installation of electric heat will increase the amount of energy used per year. Savings are realized from lower demand charges, less gas consumption, and CP&L Rider 4.
(2) Implementation cost includes CP&L’s rebate of approximately $57,500 ($18.40/ton).
(3) ECRM is not recommended therefore this amount is not included in the totals below.
(4) Implementation Cost includes 7% Engineering fee.
Bldg. ID : Entire Campus
TABLE 2. BASE YEAR ENERGY CONSUMPTION DATA Gross Square Footage: 1,695,000
For prior 12 month period beginning August, 1996 and ending July, 1997
|
Historical Load Data |
|
|
|
|
|
|
|
|
|
|
|
|
|
Month |
Aug-96 |
Sep-96 |
Oct-96 |
Nov-96 |
Dec-96 |
Jan-97 |
Feb-97 |
Mar-97 |
Apr-97 |
May-97 |
Jun-97 |
Jul-97 |
|
Maximum Demand kW |
6,039 |
6,181 |
6,342 |
5,921 |
5,524 |
4,084 |
5,248 |
5,256 |
5,413 |
5,482 |
5,745 |
5,933 |
|
KWh |
3,132,900 |
3,242,100 |
3,381,600 |
3,122,700 |
2,272,500 |
2,058,000 |
2,100,300 |
2,293,200 |
2,405,100 |
2,628,300 |
3,141,300 |
3,246,900 |
|
Power Factor |
95.3% |
95.2% |
94.9% |
96.6% |
98.6% |
99.9% |
99.6% |
96.7% |
96.0% |
94.4% |
92.6% |
92.1% |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
State Institutional Service - 45 |
|
|
|
|
|
|
|
|
|
|
|
|
|
Billing kW (adjusted for PF) |
5,911 |
6,052 |
6,218 |
5,765 |
5,334 |
3,922 |
5,046 |
5,115 |
5,283 |
5,386 |
5,685 |
5,883 |
|
Max Billing kW previous summer |
6,218 |
6,218 |
6,218 |
6,218 |
6,218 |
6,218 |
6,218 |
6,218 |
6,218 |
6,218 |
6,218 |
6,218 |
|
Billing kW |
5,911 |
6,052 |
6,218 |
5,765 |
5,334 |
4,974 |
5,046 |
5,115 |
5,283 |
5,386 |
5,685 |
5,883 |
|
Demand Charge, $13.13/kW |
77,611 |
79,463 |
81,642 |
75,694 |
70,035 |
65,314 |
66,254 |
67,160 |
69,366 |
70,718 |
74,644 |
77,244 |
|
Energy Charge, $0.00779/kWh |
24,405 |
25,256 |
26,343 |
24,326 |
17,703 |
16,032 |
16,361 |
17,864 |
18,736 |
20,474 |
24,471 |
25,293 |
|
Educational Institution Discount |
-20,403 |
-20,944 |
-21,597 |
-20,004 |
-17,548 |
-16,269 |
-16,523 |
-17,005 |
-17,620 |
-18,239 |
-19,823 |
-20,507 |
|
Fuel Charge Rate, $/kWh |
$0.013702 |
$0.013702 |
$0.013702 |
$0.013702 |
$0.013702 |
$0.015249 |
$0.015249 |
$0.017652 |
$0.017652 |
$0.017652 |
$0.017652 |
$0.015164 |
|
Fuel Charge |
42,927 |
44,423 |
46,335 |
42,787 |
31,138 |
31,382 |
32,027 |
40,480 |
42,455 |
46,395 |
55,450 |
49,236 |
|
Gross Receipts Fee Adjustment |
3,593 |
3,699 |
3,829 |
3,543 |
2,923 |
2,783 |
2,831 |
3,130 |
3,258 |
3,443 |
3,887 |
3,787 |
|
Transformer Rental |
768 |
768 |
768 |
768 |
768 |
768 |
768 |
768 |
768 |
768 |
768 |
768 |
|
Facilities Rental |
4,134 |
4,134 |
4,134 |
4,134 |
4,134 |
4,134 |
4,134 |
4,134 |
4,134 |
4,134 |
4,134 |
4,134 |
|
Total |
133,035 |
136,799 |
141,454 |
131,248 |
109,154 |
104,144 |
105,852 |
116,531 |
121,096 |
127,694 |
143,531 |
139,955 |
|
Total Electric for Year |
$1,510,494 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Gas Heat |
|
|
|
|
|
|
|
|
|
|
|
|
|
Gas MCF |
0 |
0 |
0 |
0 |
657 |
2,361 |
2,177 |
0 |
0 |
0 |
0 |
0 |
|
Cost of gas, $/MCF |
3.69 |
3.69 |
3.69 |
3.69 |
3.69 |
3.69 |
3.69 |
3.69 |
3.69 |
3.69 |
3.69 |
3.69 |
|
Total |
0 |
0 |
0 |
0 |
2,424 |
8,712 |
8,033 |
0 |
0 |
0 |
0 |
0 |
|
Total Gas for Year |
$19,170 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Total Electric & Gas for Year |
$1,529,663 |
|
|
|
|
|
|
|
|
|
|
|
|
|
Electricity |
Natural Gas |
Other |
|
Company Name: |
Central Power & Light |
General Land Office |
Entex (Gas transportation) |
|
Company Rate Schedule |
Rate 45 with Rider 4 |
*Certification:
Charges have been recomputed and are correct
METERING INFORMATION
TABLE 3. METER DATA
|
Meter Number |
Area Served |
|
Electric
2224 12637 12637 (Reactive)
|
These two meters serve the facilities affected by the ECRMs. The meters are combined on a single bill for electric service. The resulting peak demand is actually the coincident peak demand and not the sum of the individual peak demands. |
|
Natural Gas
417893 6070253 71729 2393257 (No longer in service) 5229992 (No longer in service)
|
Main Meter (Entire Campus except the following) Javelina Stadium Poteet Hall Athletic Office May Hall Area |
UTILITY RATE SCHEDULE ANALYSIS
ELECTRIC UTILITY RATE SCHEDULE ANALYSIS
NAME OF UTILITY:
Central Power & Light (CP&L)
RATE SCHEDULE ANALYZED:
Rate 45 with Rider 4, Rider 30 & S-TOU (See Appendix C)
SUMMARY OF BILLING COMPONENT CHARGES:
|
State Institutional Service – 45 |
|
|
|
|
|
|
|
|
|
Demand $/kW |
$13.13 |
|
|
|
|
|
|
|
Minimum Demand Charge |
$3.54 |
per hp of largest motor |
|
|
|
|
|
|
Energy Charge |
$0.00779 |
|
|
|
|
|
|
|
Fuel Cost |
|
|
|
|
|
|
|
|
Demand = 15 minutes of max usage for month |
|
|
|
|
|
|
|
|
Minimum Demand = 80% of July-Oct peak |
|
|
|
|
|
|
|
|
Minimum Demand = 600 kW |
|
|
|
|
|
|
|
|
Power Factor > 90%: decrease demand by 0.4% for each 1% |
|
|
|
|
|
|
|
|
Power Factor < 80%: increase demand by 0.4% for each 1% |
|
|
|
|
|
|
|
|
Transmission Discount = $0.50 per kW if customer owns, operates, and maintains HV facilities |
|
|
|
|||
|
|
|
|
|
|
|
|
|
|
Space Heating – Rider 4 |
|
|
|
|
|
|
|
|
|
Demand = greater of: (max measured demand for month or max measured demand for |
|
|
|
|
||
|
|
6 months preceding winter months) less 1 kW for each ton of HVAC |
|
|
|
|
|
|
|
|
Minimum Demand = 50% of measured demand for month |
|
|
|
|
|
|
|
|
Minimum Demand = 50% of peak demand in 6 months preceding winter months |
|
|
|
|
||
|
|
Maximum Demand = measured demand for present month |
|
|
|
|
|
|
|
|
Winter Months = November – April |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
State Educational Institution Discount – Rider 30 |
|
|
|
|
|
|
|
|
|
20% off of base rate [kW & kWh], but not on fuel or rental charges |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Base Rate Fixed Fuel Cost Factor (as of 8/26/97) |
|
|
|
|
|
|
|
|
|
January – February (primary) $/kWh |
$0.015249 |
|
|
|
|
|
|
|
March - June (primary) |
$0.017652 |
|
|
|
|
|
|
|
July (primary) |
$0.015164 |
|
|
|
|
|
|
|
August – December (primary) $/kWh |
$0.013702 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Select Time Of Use (S-TOU) |
|
|
|
|
|
|
|
|
|
On-Peak Season = June, July, Aug, Sept |
|
|
|
|
|
|
|
|
Off-Peak Season = Oct, Nov, Dec, Jan, Feb, Mar, Aprl, May |
|
|
|
|
|
|
|
|
On-Peak Hours: |
|
|
|
|
|
|
|
|
Narrow Window = 3:00 pm thru 7:00 pm weekdays during On-Peak Season |
|
|
|
|
|
|
|
|
Standard Window = 2:00 pm thru 8:00 pm weekdays during On-Peak Season |
|
|
|
|
|
|
|
|
Wide Window = 1:00 pm thru 9:00 pm weekdays during On-Peak Season |
|
|
|
|
|
|
|
|
Off-Peak Hours = all other hours + all Off-Peak Season Hours + July 4 + Labor Day |
|
|
|
|
||
|
|
|
Pricing |
A |
B |
C |
|
|
|
Narrow Window |
Pp |
8.20 |
9.70 |
11.80 |
Cents/kWh |
|
|
|
Po |
3.35 |
3.30 |
3.20 |
Cents/kWh |
|
|
Standard Window |
Pp |
8.20 |
9.70 |
11.80 |
Cents/kWh |
|
|
|
Po |
3.25 |
3.15 |
3.00 |
Cents/kWh |
|
|
Wide Window |
Pp |
8.20 |
9.70 |
11.80 |
Cents/kWh |
|
|
|
Po |
3.15 |
3.00 |
2.80 |
Cents/kWh |
|
|
Monthly Bill = EC + DC + Pgm |
|
|
|
|
|
||||||||||
|
|
|
|
|
|
|
|||||||||||
|
|
Pgm = Program Charge = $10 per month |
|
|
|
|
|
||||||||||
|
|
|
|
|
|
||||||||||||
|
|
EC = Energy Charge = (kWho x Po) + kWhp x Pp) |
|
|
|
|
|||||||||||
|
|
kWho = Customer’s current actual monthly off-peak kWh usage |
|
|
|
|
|||||||||||
|
|
kWhp = Customer’s current actual monthly on-peak kWh usage |
|
|
|
|
|||||||||||
|
|
Po = Applicable monthly off-peak S-TOU price |
|
|
|
|
|||||||||||
|
|
Pp = Applicable monthly on-peak S-TOU price |
|
|
|
|
|||||||||||
|
|
|
|
|
|
||||||||||||
|
|
DC = Delivery Charge = {Base Bill -[(kWho x Po) + (kWhp x Pp)]} / 12 months ; DC >= $0 |
|
|
|
|
|||||||||||
|
|
kWho = Annual Customer User Profile off-peak kWh usage for 12 month period |
|
|
|
|
|
||||||||||
|
|
kWhp = Annual Customer User Profile on-peak kWh usage for 12 month period |
|
|
|
|
|
||||||||||
|
|
Po = Applicable off-peak S-TOU price for 12 month period |
|
|
|
|
|
||||||||||
|
|
Pp = Applicable on-peak S-TOU price for 12 month period |
|
|
|
|
|
||||||||||
|
|
Base Bill = Annual Customer Usage Profile under standard rate schedule and riders |
|
|
|
|
|
||||||||||
AVOIDED COST OF ENERGY TO BE USED IN CALCULATIONS:
Base Energy Charge less 20% Institutional Discount = $0.00779 x 0.8 = $ 0.00623 per kWh used
+ Average Fuel Charge = $ 0.01540 per kWh used
Base + Fuel Charge = $ 0.02163 per kWh used
x Gross Receipts Factor = x 1.02885
Avoided Cost of Energy = $ 0.02225 per kWh used
AVOIDED COST OF DEMAND TO BE USED IN CALCULATIONS:
Demand Charge less 20% Institutional Discount = $13.13 x 0.8 = $ 10.50 per kW
x Gross Receipts Factor = x 1.02885
Avoided Cost of Demand = = $ 10.80 per kW
COMMENTS:
Rider 4 - Space Heating
Rate 45 with Rider 4 is used to evaluate ECRM’s 1, 2, 3, 4, 5, and 6. Rider 4 gives the customer a demand credit in the summer months which is proportional to the customer’s electric air conditioning capacity when the customer uses electricity for providing heat. Since TAMU-K is installing electric heat which is ECRM 1, the remaining ECRM’s must be evaluated with Rider 4.
Select Time of Use (S-TOU)
S-TOU is the rate used to evaluate ECRM 6 in lieu of Rate 45. At first look, it appears that the S-TOU rate encourages thermal energy storage by the fact that it has no demand component and that the energy charge (EC) during the off-peak hours is considerably less than the on-peak hours. Further, the wider the on-peak window the customer selects, the lower the off-peak energy charge. However, in addition to the energy charge there is a delivery charge (DC) which as stated in the rate is designed to achieve revenue neutrality with the customer’s standard rate schedule. In other words, the delivery charge adds back into the bill the difference between the energy charge under S-TOU and the customer’s bill as would have been calculated under the customer’s previous rate for the previous year. It appears that this rate would only offer savings to a customer that is expecting a large increase in electrical usage.
GAS UTILITY RATE SCHEDULE ANALYSIS
NAME OF UTILITY:
General Land Office for gas
Entex for transportation
RATE SCHEDULE ANALYZED:
SUMMARY OF BILLING COMPONENT CHARGES:
TAMU-K is billed for the quantity of gas used by the General Land Office. It is billed for the delivery of that gas by Entex. Entex bills are based on the quantity of gas delivered to TAMU-K.
AVOIDED COST OF ENERGY TO BE USED IN CALCULATIONS:
The cost of gas used in the analysis is the average cost of gas for the past 12 months which is $3.69/MCF. Appendix D contains tabulated monthly gas consumption data for January1993 through July 1997.
AVOIDED COST OF DEMAND TO BE USED IN CALCULATIONS:
Not Applicable.
COMMENTS:
FACILITY DESCRIPTIONS
The following is a brief summary of the existing conditions in each building affected by the ECRMs. Refer to Appendix G for a detailed schedule of the existing building systems.
Lynch Hall
Lynch Hall is a two story building served from the two-pipe system. This building contains six (6) multizone air handling units (AHUs) with face and bypass dampers and a total of 19 zones. Each AHU has a 3-way control valve.
An electric duct heater will be installed in each of the AHU zones (ECRM No.1); the 3-way valves will be replaced with 2-way valves (ECRM No. 4); and the electric heat will be controlled through the Energy Management System (ECRM No.3).
Poteet Hall
Poteet Hall Unit A is a one story building served from the two-pipe system. Poteet Hall Unit B is a three story building also served from the two-pipe system. This building contains two (2) multizone AHUs with face and bypass dampers and twelve (12) single zone AHUs for a total of 19 zones. Each AHU has a 3-way control valve.
An electric duct heater will be installed in each of the AHU zones (ECRM No.1); the 3-way valves will be replaced with 2-way valves (ECRM No. 4); and the electric heat will be controlled through the Energy Management System (ECRM No. 3).
Jernigan Library
Jernigan Library is a three story building containing four (4) double duct AHUs and electric heat. Each AHU has a 3-way control valve.
The 3-way valves will be replaced with 2-way valves (ECRM No. 4).
Industrial Technology
Industrial Technology is a one story building served from the four-pipe system. This building contains two (2) multizone AHUs and two (2) single zone AHUs with a total of 12 zones. Each AHU has a 3-way control valve.
The 3-way valves will be replaced with 2-way valves (ECRM No. 4).
Eckhardt Hall
Eckhardt Hall is a two story building served from the two-pipe system. This building contains 5 multizone AHUs and 1 single zone AHU with a total of 17 zones. Each AHU has a 3-way control valve.
An electric duct heater will be installed in each of the AHU zones (ECRM No.1); the 3-way valves will be replaced with 2-way valves (ECRM No. 4); the electric heat will be controlled through the Energy Management System (ECRM No. 3).
Dotterweich Engineering Hall
Dotterweich Engineering Hall is a one story building with two AHUs. AHU-1 (double duct) is served solely from the four-pipe system while AHU-2 (roof top, single zone) can be served from either the four-pipe system or a local chiller. Each AHU has a 3-way control valve.
The 3-way valve for AHU-1 will be replaced with a 2-way valve (ECRM No. 4). The 3-way valve at AHU-2 will remain if it is going to continue to operate with local chiller.
Student Union/Bookstore
The Student Union is a three story building that contains 17 AHUs and its own boilers. All AHUs have 2-way valves. The Bookstore is a one story building that receives hot water from the boilers in the Student Union and has 1 AHU with 3-way chilled water control valve.
The 3-way valve in the Bookstore will be replaced with a 2-way valve (ECRM No. 4).
Biology-Earth Science
Biology-Earth Science is a three story building served from the two-pipe system. The building contains 1 single zone AHU and 2 multizone AHUs with a total of 15 zones. Each AHU has a 3-way control valve.
An electric duct heater will be installed in each of the AHU zones (ECRM No.1); the 3-way valves will be replaced with 2-way valves (ECRM No. 4); and the electric heat will be controlled through the Energy Management System (ECRM No.3).
Kleberg Engineering Bldg
Kleberg Engineering is a one story building with 2 single zone AHUs and 2 Multizone AHUs with a total of 13 zones. Each AHU has a 3-way control valve. This building is served from the four-pipe system.
The 3-way valves will be replaced with 2-way valves (ECRM No. 4).
Steinke Physical Education Center
Steinke Physical Education Center is a 3 story building served from the four-pipe system. The building contains 4 multizone AHUs and 6 single zone AHUs with a total of 30 zones. Six of the AHUs have 3-way control valves. The other four have 2-way valves.
The 3-way valves will be replaced with 2-way valves (ECRM No. 4).
College Hall
College Hall is a three story building served from the two-pipe system. The building contains 2 single zone AHUs (one with both a DX and chilled water coil) and 4 multizone AHUs with a total of 27 zones. There are 5 3-way control valve.
An electric duct heater will be installed in each of the AHU zones (ECRM No.1); the 3-way valves will be replaced with 2-way valves (ECRM No. 4); and the electric heat will be controlled through the Energy Management System (ECRM No.3).
Bellamah Music
Bellamah Music is a two story building served from the two-pipe system. The building contains 3 single zone AHUs and 3 multizone AHUs with a total of 10 zones. Each AHU has a 3-way control valve.
An electric duct heater will be installed in each of the AHU zones (ECRM No.1); the 3-way valves will be replaced with 2-way valves (ECRM No. 4); and the electric heat will be controlled through the Energy Management System (ECRM No.3).
Speech Bldg
Speech is a two story building served from the two-pipe system. This building contains 1 single zone AHU and 1 multizone AHU with a total of 4 zones. Each AHU has a 3-way control valve.
An electric duct heater will be installed in each of the AHU zones (ECRM No.1); the 3-way valves will be replaced with 2-way valves (ECRM No. 4); and the electric heat will be controlled through the Energy Management System (ECRM No.3).
Bailey Arts Bldg
Bailey Arts is a one story building served from the two-pipe system. The building contains 1 multizone AHU with a total of 3 zones. There is 1 3-way control valve.
An electric duct heater will be installed in each of the AHU zones (ECRM No.1); the 3-way valve will be replaced with 2-way valves (ECRM No. 4); and the electric heat will be controlled through the Energy Management System (ECRM No.3).
Art Addition
Art Addition is a 1 story building served from the two-pipe system. The building contains 2 multizone AHUs with a total of 8 zones. Each AHU has a 3-way control valve.
An electric duct heater will be installed in each of the AHU zones (ECRM No.1); the 3-way valves will be replaced with 2-way valves (ECRM No. 4); and the electric heat will be controlled through the Energy Management System (ECRM No.3).
ROTC Bldg
ROTC is a one story building served from both the two-pipe and the four-pipe systems. The building contains 1 multizone AHU (3 zones) and 2 single zone AHUs. The multizone is the only AHU served from the two pipe system. All AHUs have 3-way control valves.
An electric duct heater will be installed in 3 AHU zones (ECRM No.1); the 3-way valves will be replaced with 2-way valves (ECRM No. 4); and the electric heat will be controlled through the Energy Management System (ECRM No.3).
Fore Hall
Fore Hall is a two story building served from the two-pipe system. This building contains 3 single zone AHUs and 1 multizone AHU with a total of 9 zones requiring electric heat. Of the 3 single zone AHUs, one currently has electric heat. Only one AHU has a 3-way control valve.
An electric duct heater will be installed in 3 AHU zones (ECRM No.1); the 3-way valves will be replaced with 2-way valves (ECRM No. 4); and the electric heat will be controlled through the Energy Management System (ECRM No.3).
Health & Recreation Bldg
Health & Recreation is a two story building served from the two-pipe system. This building contains 1 single zone AHU and 2 multizone AHUs with a total of 11 zones. Each AHU has a 3-way control valve.
An electric duct heater will be installed in each of the AHU zones (ECRM No.1); the 3-way valves will be replaced with 2-way valves (ECRM No. 4); and the electric heat will be controlled through the Energy Management System (ECRM No.3).
Martin Hall
Martin Hall is a three story building served from the two-pipe system. This building contains 14 multizone AHUs with a total of 56 zones. Each AHU has a 3-way control valve.
An electric duct heater will be installed in each of the AHU zones (ECRM No.1); the 3-way valves will be replaced with 2-way valves (ECRM No. 4); and the electric heat will be controlled through the Energy Management System (ECRM No.3).
Turner-Bishop Hall
Turner-Bishop Hall is a three story building served from the two-pipe system. This building contains 16 multizone AHUs with a total of 71 zones. Each AHU has a 2-way control valve.
An electric duct heater will be installed in each of the AHU zones (ECRM No.1) and the electric heat will be controlled through the Energy Management System (ECRM No.3).
Hill Hall
Hill Hall is a two story building served from the two-pipe system. This building contains 6 single zone AHUs, however, 4 of the 6 will require two duct heaters due to duct splits (10 heaters total). Each AHU has a 3-way control valve.
An electric duct heater will be installed in each of the AHU zones (ECRM No.1); the 3-way valves will be replaced with 2-way valves (ECRM No. 4); and the electric heat will be controlled through the Energy Management System (ECRM No.3).
Nierman Hall
Nierman Hall is a two story building served from the two-pipe system. This building is being renovated under a separate contract to install electric heat. There are 5 AHUs, each with a 3-way control valve.
The 3-way valves will be replaced with 2-way valves (ECRM No. 4).
Howe Agriculture Bldg
Howe Agriculture is a two story building which contains a local boiler. This building also contains 2 AHUs, each with 3-way control valves.
The 3-way valves will be replaced with 2-way valves (ECRM No. 4).
Business Administration
Business Administration is a two story building containing 4 multizone AHUs with existing electric heat. Each of the AHUs has a 3-way control valve.
The 3-way valves will be replaced with 2-way valves (ECRM No. 4).
Kleberg Agriculture Bldg
Kleberg Agriculture is a one story building served from the two-pipe system. This building contains 3 single zone AHUs and 1 multizone AHU. Each of the single zone AHUs will require two duct heaters due to duct splits. Therefore, 10 heaters will be required. Each AHU has a 3-way control valve.
An electric duct heater will be installed in each of the AHU zones (ECRM No.1); the 3-way valves will be replaced with 2-way valves (ECRM No. 4); and the electric heat will be controlled through the Energy Management System (ECRM No.3).
Manning Hall
Manning Hall is a two story building served from the two pipe system. This building is being renovated under a separate contract to install electric heat. There are 8 multizone AHUs, each with 3-way control valves; the 3-way valves will be replaced with 2-way valves (ECRM No. 4).
Student Health Center
Student Health Center is a one story building served from the two-pipe system. This building contains 1 multizone AHU with 4 zones and a 3-way control valve.
An electric duct heater will be installed in each of the AHU zones (ECRM No.1); the 3-way valves will be replaced with 2-way valves (ECRM No. 4); and the electric heat will be controlled through the Energy Management System (ECRM No.3).
Human Sciences Bldg
Human Sciences is a one story building served from the two-pipe system. This building contains 2 multizone AHUs with a total of 10 zones. Each AHU has a 3-way control valve.
An electric duct heater will be installed in each of the AHU zones (ECRM No.1); the 3-way valves will be replaced with 2-way valves (ECRM No. 4); and the electric heat will be controlled through the Energy Management System (ECRM No.3).
Lewis Hall
Lewis Hall is a three story building served from the two-pipe system. This building contains 7 multizone AHUs with a total of 16 zones and 3 single zones AHUs. Nine of the ten AHUs have 3-way control valves. The tenth AHU does not have a chilled water coil (DX & steam coils only). This buildings also contains three steam boilers and a steam to hot water converter to produce its own heating water. However, the AHUs only have one coil and they do not have the ability to simultaneously heat and cool.
An electric duct heater will be installed in each of the AHU zones which do not currently have a heating coil (ECRM No.1); the 3-way valves will be replaced with 2-way valves (ECRM No. 4); and the electric heat will be controlled through the Energy Management System (ECRM No.3).
TECHNICAL ANALYSIS
Note: All calculations relevant to ECRM savings are in Appendix A.
ENERGY COST REDUCTION MEASURES (ECRMs) - DETAILED CALCULATIONS
ECRM NO.: 1
ECRM NAME: Install Electric Heat
SUMMARY DATA (DEPENDENT)
kWh Savings: <542,760> kWh/Year
Demand Savings: 10,737 kW/yr.
Gas Savings: 5195 MCF/yr.
Cost Savings: $134,760 /yr.
Implementation Cost: $ 1,132,060 $
Simple Payback: 8.4 Years
Estimated Useful Life: 25 Years
ECRM No. 1 DESCRIPTION
There are 27 buildings connected to the two-pipe thermal distribution system. Four of these buildings have heating water boilers; another six buildings have electric heat. This means that as long as the two-pipe system is in the cooling mode, these 10 buildings can be heating or cooling as necessary. The remaining 17 buildings will all cool or heat depending on the mode of the two-pipe system. Further, when the two-pipe system is in the heating mode, the 10 buildings which have local heating capabilities cannot do any cooling.
There are 5 buildings connected to a pseudo-four-pipe system. It is not a true four-pipe system in that the chilled water piping is served from the two-pipe system. Therefore, when the two-pipe system is in heating mode, these 5 buildings receive all hot water.
The two-pipe system not only creates building comfort problems, it consumes a significant amount of energy to heat the chilled water when converting to heating and even more energy to cool the hot water when converting to cooling. In an effort to increase their ability to better control building comfort and reduce the energy waste inherent to cycling between hot and cold water, TAMU-K is installing electric heat in the applicable buildings.
The electric heat will increase the electricity consumption, but will reduce the gas consumption. Typically, electric heat costs more on an energy basis; however, CP&L’s Rider 4, when applied, provides a net savings to TAMU-K. Rider 4 gives the customer a demand credit for electric air conditioning when electric heat is used. SSA prepared models of CP&L’s utility rates and used kW and kWh for the months of August 1996 through July 1997 as a base for comparing Rate 45 against Rate 45 with Rider 4. Refer to Appendix A, pg. A-1 and A-2 for the cost comparison calculations labeled “Current Usage & Rate” and “Electric Heat with Rider 4”, respectively. The savings are the difference between the annual electric and gas costs calculated in each model.
See Appendix B for monthly electric bills and Appendix C for CP&L Rates.
ECRM No. 1 ASSUMPTIONS
To determine the amount of gas utilized for building heat, SSA reviewed past utility bills and determined an average gas usage for non-heating months (March through November) and for heating months (December through February). The difference was the amount of gas used for building heat. Based on the total square footage of buildings heated by gas, SSA estimated that the buildings served from the existing two-pipe system comprised 74% of the total.
To determine the amount of additional electrical energy consumed by utilizing electric heat, SSA used the total installed heating kW and assumed 10 heating days at 24 hrs/day and a 50% average load during heating. This assumption is based on the operating personnel’s experience that the two pipe system is in the heating mode 12 to 15 days per year, typically for half of each day. Based on the foregoing, SSA estimated an annual heating energy requirement of 543,000 kWh for the buildings now served by the two pipe system. This amount was apportioned between three heating months (December, January and February).
The impact of electrical heating demand will only apply to three months out of the year. Even in these months, the maximum heating demand will never coincide with the peak campus electrical demand for the month. The highest demand for heating will be early in the morning when the buildings are being heated up. A review of time-of-day load data for January and February indicates that early morning loads are typically 2000-3000 kW less that the maximum monthly demand (see Appendix I). Any heat demand up to this level will not increase the electrical demand cost. By staging the startup of the building heat, it will be possible to minimize any contribution of heating loads to the monthly demand. For purposes of this evaluation, we have assumed that the electrical demand kW for the months of December, January and February would increase by an amount equal to one third of the total electrical heating demand.
ECRM NO.: 2
ECRM NAME: Replace Chillers
SUMMARY DATA (DEPENDENT)
kWh Savings: 2,395,876 kWh/Year
Demand Savings: 10,337 kW/yr.
Gas Savings: 0 MCF/yr.
Cost Savings: $97,836 /yr.
Implementation Cost: $ 1,594,000 $
Simple Payback: 16.3 Years
Estimated Useful Life: 25 Years
ECRM No. 2 DESCRIPTION
TAMU-K currently has 4500 tons of chiller capacity divided between two central plants. Central Plant 1 has 2-250 ton chillers, 1-500 ton chiller and 1-1000 ton chiller. Central Plant 2 has 2-750 ton chillers and 1-1000 ton chiller. The chillers range in age from 21 years to 38 years with an overall average age of 31 years. TAMU-K indicates that the average chiller efficiency is 0.90 kW/ton which is based on field measurements. All chillers use R-11.
TAMU-K has decided to replace these units with high efficiency non-CFC chillers. Central Plant 1 will receive 2-625 ton units with space for a third future 625 ton chiller. Central Plant 2 will get 3-625 ton chillers. In total, TAMU-K will have 3125 tons* of chiller capacity. The chillers will have a minimum efficiency of 0.62 kW/ton.
Currently TAMU-K’s peak cooling demand is estimated to be 2500 tons based on the operating personnel’s experience and the Trace analysis included in Appendix E (Input) and Appendix F (Output). The Trace analysis also provided the thermal load profile for evaluating the savings from the new chillers.
Refer to Appendix A, pg. A-3 for savings calculations labeled “Improved Chiller Efficiency combined with Electric Heat under Rider 4”. The savings are the difference between the annual electrical cost calculated in this model and the annual cost calculated for electric heat under ECRM No. 1 (Appendix A, pg. A-2 - “Electric Heat with Rider 4”).
ECRM No. 2 ASSUMPTIONS
TAMU-K does not record thermal utility data for their chilled water system. Therefore SSA used TRACE load calculation software to determine the thermal profile for the campus buildings served from the existing central plants. From the campus profile, the monthly peak load and ton-hours were calculated for use in the savings calculations.
* Central Plant 1 actually received 3-650T chillers as did Central Plant #2 for a total capacity of 3900 tons.
ECRM NO.: 3
ECRM NAME: Install Energy Management System
SUMMARY DATA (DEPENDENT)
kWh Savings: 0 kWh/Year
Demand Savings: 1,036 kW/yr.
Gas Savings: 0 MCF/yr.
Cost Savings: $11,200 /yr.
Implementation Cost: $ 159,430 $
Simple Payback: 14.2 Years
Estimated Useful Life: 25 Years
ECRM No. 3 DESCRIPTION
Installation of an Energy Management System (EMS) in each of the buildings receiving electric heat under ECRM No. 1 will be required for staging the electric heating to maximize the demand savings.
The EMS will be configured to monitor campus electrical demand and will limit the number of electric heaters operating so as to not set a peak demand above that which would normally be set without electric heat.
Refer to Appendix A, pg. A-4 for savings calculations labeled “Electric Heat with Rider 4 & EMS Control”. The savings are the difference between the annual electrical cost calculated in this model and the annual cost calculated for electric heat without EMS control under ECRM No. 1 (Appendix A, pg. A-2 - “Electric Heat with Rider 4”).
ECRM No. 3 ASSUMPTIONS
The analysis of ECRM No. 3 uses the same procedure as that used for ECRM No. 1 except that the affect of the electric heat on the peak electrical demand, referred to in the calculations as “coincident factor”, is set to zero. Therefore, the assumptions used to evaluate ECRM No. 1 are inherent to this analysis.
ECRM NO.: 4
ECRM NAME: Replace 3-Way with 2-Way Valves
SUMMARY DATA (DEPENDENT)
kWh Savings: 248,000 kWh/Year
Demand Savings: 896 kW/yr.
Gas Savings: 0 MCF/yr.
Cost Savings: $15,222 /yr.
Implementation Cost: $ 160,500 $
Simple Payback: 10.5 Years
Estimated Useful Life: 25 Years
ECRM No. 4 DESCRIPTION
Replace the majority of the 114 existing 3-way valves with 2-way valves at building AHUs to reduce pumping energy at low load conditions. Some existing 3-way valves will remain in the system to maintain minimum flow requirements.
Refer to Appendix A, pg. A-5 for savings calculations labeled “Electric Heat with Rider 4 & 2-way Valves”. The savings are the difference between the annual electrical cost calculated in this model and the annual cost calculated for electric heat with 3-way valves under ECRM No. 1 (Appendix A, pg. A-2 - “Electric Heat with Rider 4”).
ECRM No.4 ASSUMPTIONS
SSA used TRACE energy analysis software to determine the campus load profile (Appendix F). From this, SSA determined the number of hours/year at each 5% increment of total load. The load data was then used to determine the chilled water flow required from the central plants based on 3-way valves and 2-way valves at the AHUs.
A hydraulic model of the campus chilled water distribution system was developed using KYPipe software. The flow data derived from the TRACE analysis was then entered into the model to determine the pumping requirements at the various load conditions for 3-way and 2-way valves. The input and output files for KYPipe are included in Appendix H. The pumping power for the 3-way valves was then compared with the 2-way valves to determine the net savings (See Appendix A, pg. A-8 & A-9). Assumptions used to arrive at the pumping requirements for the two types of control valves are discussed below.
3-Way Valves
This model represents the existing conditions. To determine the flow rates in the system, SSA assumed a chilled water differential temperature (DT) of 7 °F. TAMU-K indicated that the typical system DT ranges between 6°F to 8°F.
Because 3-way valves create a constant volume/head system, the hydraulic model maintained a constant flow and head at each load increment. The flow and head are reduced as chillers and their associated pumps are taken off line. At 100%, the load requires four chillers to be run and at 80% load only three chillers are required. Therefore, the required flow for four chillers, 8742 gpm was held constant for each increment that required four chillers (100% down to 85%). The required flow for three chillers, 7431 gpm was held constant for each increment that required three chillers (80% down to 60%) and so on.
2-Way Valves
By replacing the existing 3-way valves with 2-way valves, the system differential temperatures can be raised by several degrees. SSA assumed that the DT would be raised to 10 °F. This is conservative based on the fact that most coils are selected for 12°F DT. This increase in DT will significantly reduce the required flow and consequently reduce the head requirements of the primary pumps.
In addition, 2-way valves allow the flow to decrease as the load decreases. Therefore, at each increment of total load, the corresponding required flow will decrease. Although the head remains somewhat constant, by reducing the amount of flow, the pumping energy is reduced.
Demand Savings
It was assumed that the campus thermal profile parallels the electrical load profile. Therefore, SSA estimated the monthly demand savings by determining the monthly thermal peak and used the demand savings that corresponds to the respective percentage of the total campus load. For example, if the monthly campus thermal peak was 1900 tons (75%), the corresponding monthly demand savings was 41 kW.
ECRM NO.: 5
ECRM NAME: Install VFDs on Primary Chilled Water Pumps
SUMMARY DATA (DEPENDENT)
kWh Savings: 15,171 kWh/Year
Demand Savings: 12 kW/yr.
Gas Savings: 0 MCF/yr.
Cost Savings: $316 /yr.
Implementation Cost: $ 85,600 $
Simple Payback: N/A Years
Estimated Useful Life: 25 Years
ECRM No. 5 DESCRIPTION
The installation of VFDs on the primary chilled water pumps in the two central is an extension of ECRM No. 4. VFDs cannot be installed unless the existing 3-way valves are replaced with 2-way valves. The intent of this ECRM is to further reduce the pumping energy requirements of the system.
The hydraulic model created for the two way valves in ECRM No. 4 was modified to determine the pumping requirements for VFDs at the various loads. The savings from the VFDs come from the turn down available between increments of chiller capacity, i.e., once the chilled water demand drops below the capacity that can be handled with one less chiller, a chiller and pump are taken off-line. The analysis indicated that there would be little savings attributable to the VFDs, therefore, SSA does not recommend pursuing ECRM No. 5.
Refer to Appendix A, pg. A-6 for savings calculations labeled “Electric Heat with Rider 4 & VFDs”. The savings are the difference between the annual electrical cost calculated in this model and the annual cost calculated for electric heat with 2-way valves under ECRM No. 4 (Appendix A, pg. A-5 - “Electric Heat with Rider 4& 2-way Valves”).
ECRM No. 5 ASSUMPTIONS
The assumptions are the same as ECRM No. 4 with one exception. With 2-way valves, only the flow can be reduced as the load decreases. The head requirements essentially remain constant. With VFDs, the pump head requirements would decrease as well as the flow to further reduce the required pump energy.
ECRM NO.: 6
ECRM NAME: Install Thermal Storage
SUMMARY DATA (DEPENDENT)
kWh Savings: 0 kWh/Year
Demand Savings: 9652 kW/yr.
Gas Savings: 0 MCF/yr.
Cost Savings: $ 91,665 /yr.
Implementation Cost: $ 856,000 $
Simple Payback: N/A Years
Estimated Useful Life: 25 Years
ECRM No. 6 DESCRIPTION
A thermal storage system adequate to provide a full shift will require approximately 14,000 ton hours of capacity. This system will cost approximately $1,225,000. The CP&L thermal storage incentive rebate will pay approximately $425,000 of this cost, leaving a net cost for the project of $800,000.
However, current CP&L rates do not encourage thermal storage. The Select Time of Use (S-TOU) Rate is the rate used to evaluate ECRM 6. At first look, it appears that the S-TOU rate encourages thermal energy storage by the fact that it has no demand component and that the energy charge (EC) during the off-peak hours is considerably less than the on-peak hours. Further, the wider the on-peak window the customer selects, the lower the off-peak energy charge. However, in addition to the energy charge there is a delivery charge (DC) which as stated in the rate is designed to achieve revenue neutrality with the customer’s standard rate schedule. In other words, the delivery charge adds back into the bill the difference between the energy charge under S-TOU and the customer’s bill as would have been calculated under the customer’s previous rate for the previous year. It appears that this rate would only offer savings to a customer that is expecting a large increase in electrical usage.
SSA also evaluated this ECRM under TAMU-K’s standard rate, Rate 45. Refer to Appendix A, pg. A-7 for the
savings calculations labeled “Electric Heat with Rider 4 plus Thermal Storage”. The savings are the difference between the annual electrical cost calculated in this model and the annual cost calculated for electric heat under ECRM No. 1 (Appendix A, pg. A-2 - “Electric Heat with Rider 4”).
This scenario seems to offer significant savings through load leveling, i.e., spreading electrical demand over 24 hours thereby lowering the campus peak demand. This approach is not very realistic. If TAMU-K were to lose their thermal storage system for some unforeseen reason, they could quite possibly set a high peak demand for that month. In addition, Rider 4 has a ratchet that could possibly set the peak for the entire year.
SSA does not recommend the implementation of this ECRM.
ECRM No. 6 ASSUMPTIONS
Had CP&L’s rates been favorable, the thermal load profile developed with TRACE along with TAMU-K’s electric profile would have provided the basis for calculating the savings and determining the size of the thermal energy storage tank.
ANALYST CERTIFICATION
The undersigned certifies that this report has been conducted in accordance with the requirements of the Texas LoanSTAR Program Technical Guidelines and Format as administered by the State Energy Conservation Office. The undersigned also certifies that the data and the cost reduction estimates presented are factual, accurate, reasonable and in accordance with generally accepted engineering practices to the best of the analyst's knowledge and that this knowledge is based on the analyst's on-site investigation of the facilities involved. The undersigned further certifies that the analyst has no undisclosed, conflicting financial interest in the recommendations of this report and agrees not to specify particular vendors or manufacturers.
The undersigned also agrees that if a recommendation of this or any other report generated under this program is implemented, that no company or association that the analyst owns or has a financial interest in, will provide products or construction for this project.
______________________________ ____________________________
Analyst's Signature Date
______________________________
Title
Affix Official P.E. Seal 67137
Texas P.E. Registration No.
The assessment report just listed was fully implemented by December of 2000 with the exception of Thermal Storage.
Water management: The university has its own water wells and periodically has them cleaned/serviced. TNRCC annually checks the condition of water being used and TAMUK does this monthly, per regulations. The cost of power, water and sewer together along with consumptive use is shown under Utility and Expenditure History (VII). Some measures being taken or soon to be taken to achieve the goal of balancing water, wastewater, energy and related costs to achieve the lowest lifecycle cost when purchasing new equipment or making modifications to existing equipment and to minimize water usage are listed below. This will apply to all campus buildings.
1. Follow SECO water efficiency guidelines for buildings and equipment where possible. See http://www.seco.cpa.state.tx.us/water_guidelines.htm
2. Water Conservation Best Management Practices (Fed. Agencies must implement no less than four of the following)-
a. Public Information and Education Programs
b.Distribution System Audits, Leak Detection & Repair
c. Water Efficient Landscaping
d.Toilets and Urinals
e. Faucets and Showerheads
f. Boiler/Steam Systems
g. Single Pass Cooling Systems
h. Cooling Tower Systems
i. Misc. High Water-Using Processes
j. Water Reuse and Recycling
3. Establish baseline usage so conservation measures can be evaluated.
4. Public Information and Education on conservation.(Utility Awareness Plan)
5. Water treatment so we can have greater than 1 cycle of concentration, likely much greater than 1 cycle.
6. Blow down from our cooling towers to be used in a “wetlands” environment, thus getting secondary usage out of it.
7. No irrigation during the day when evaporation is highest.
8. Metering both makeup and blow down water from cooling towers to ensure precise monitoring and to verify engineering standard practices.
9. Irrigation by sprinkler systems broken down into separate areas (hydro-zoned) for more detailed watering.
10. Metering all irrigation so this water is not subject to sewer costs.
This page was last updated on: July 07, 2011